Kalash Developers Associates

Company or firm · 3 projects · 3 MahaRERA registrations

3Projects3 RERA registrations
0Completedas reported on MahaRERA project pages
33%Kept RERA date1 of 3 past their proposed date, not extended
+6 moMedian delayvs RERA proposed date · 2 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Imperium ApartmentsP51600010643Nashik (M Corp.)2017Certificate Signed31 Dec 201831 Dec 2019+12 months
Swarajya ApartmentP51600033621Nashik (M Corp.)2022Certificate Signed31 Mar 202430 Sep 2024+6 months
Lotus Pride ApartmentP51600048059Nashik2022Certificate Signed30 Sep 202330 Sep 2023On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Imperium Apartments+12 mo
  • Swarajya Apartment+6 mo
  • Lotus Pride ApartmentOn date

Track record notes

  • 1 of 3 registrations whose RERA proposed completion date has passed was never extended beyond it.
  • Longest extension on record: 12 months, for Imperium Apartments (P51600010643).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology