Kachhi Properties

Company or firm · 3 projects · 3 MahaRERA registrations

3Projects3 RERA registrations
0Completedas reported on MahaRERA project pages
67%Kept RERA date2 of 3 past their proposed date, not extended
+0 moMedian delayvs RERA proposed date · 1 extended
1Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Anandgriha Phase II - A, B BuildingP52700005474Satara2017Not reported31 Dec 2018—On date
Anandgriha Phase IIIP52700007506Satara2017Not reported31 Dec 202130 Dec 2022+12 months
Anandgriha- Phase IP52700009557Hamdabaj2017Not reported28 Feb 2018—On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Anandgriha Phase II - A, B BuildingOn date
  • Anandgriha Phase III+12 mo
  • Anandgriha- Phase IOn date

Track record notes

  • 2 of 3 registrations whose RERA proposed completion date has passed were never extended beyond it.
  • Longest extension on record: 12 months, for Anandgriha Phase III (P52700007506).

Regulatory cases across projects

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology