K. Talsania Constructions
Company or firm · 4 projects · 4 MahaRERA registrations
Also appears as K TALSANIA CONSTRUCTIONS
4Projects4 RERA registrations
0Completedas reported on MahaRERA project pages
100%Kept RERA date2 of 2 past their proposed date, not extended
+0 moMedian delayvs RERA proposed date · 0 extended
0Regulatory casesMahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| Siddhi Apartment ChsP51800013801 | Borivali | 2017 | Not reported | 30 Dec 2025 | — | On date |
| Malad Shitalnath ChslP51800034499 | Borivali | 2022 | Not reported | 31 Dec 2025 | — | On date |
| Aditya Goraswadi ChslP51800080859 | Borivali | 2025 | Not reported | 31 Dec 2027 | — | On date |
| SHUBH MANGAL SRA CHS (Prop)PM1180002601196 | Malad | 2026 | Not reported | 31 Dec 2029 | — | On date |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 2 of 2 registrations whose RERA proposed completion date has passed were never extended beyond it.
- No MahaRERA regulatory order or list names these registrations.
- MahaRERA records spell this promoter's name 2 ways; all of them are linked to this page through its registrations.
Regulatory cases across projects
None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology