K N Developers And Engineers Llp
Company or firm · 2 projects · 4 MahaRERA registrations
Projects24 RERA registrations
Completed0as reported on MahaRERA project pages
Kept RERA date0%0 of 2 past their proposed date, not extended
Median delay+6 movs RERA proposed date · 2 extended
Regulatory cases0MahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| Sky VillasP52000025200 | Pen (M Cl) | 2020 | Not reported | 30 Dec 2023 | 28 Dec 2024 | +12 months |
| Sky VillasP52000028114 | Pen (M Cl) | 2021 | Not reported | 31 Jul 2024 | 31 Jul 2025 | +12 months |
| Sky VillasP52000051183 | Pen (M Cl) | 2023 | Not reported | 31 Dec 2026 | — | On date |
| Sky Tower Phase-IPR1281012502393 | Nachane (Ct) | 2026 | Not reported | 30 Jun 2028 | — | On date |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 0 of 2 registrations whose RERA proposed completion date has passed were never extended beyond it.
- Longest extension on record: 12 months, for Sky Villas (P52000025200).
- No MahaRERA regulatory order or list names these registrations.
Regulatory cases across projects
None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology