Skip to content
Deedo home
Menu

K & M Sheltors Pvt Ltd

Company or firm · 3 projects · 3 MahaRERA registrations

Also appears as K & M Sheltors Pvt. Ltd.

Projects33 RERA registrations
Completed0as reported on MahaRERA project pages
Kept RERA date100%2 of 2 past their proposed date, not extended
Median delay+0 movs RERA proposed date · 0 extended
Regulatory cases0MahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Mid Summer Chs LtdP51800008174Andheri2017Not reported31 Dec 2018—On date
The ShelterP51800030432Kurla2021Not reported31 Dec 2025—On date
HarmonyPR1180002602179Bandra-F2026Not reported31 Dec 2029—On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Mid Summer Chs LtdOn date
  • The ShelterOn date
  • HarmonyOn date

Track record notes

  • 2 of 2 registrations whose RERA proposed completion date has passed were never extended beyond it.
  • No MahaRERA regulatory order or list names these registrations.
  • MahaRERA records spell this promoter's name 2 ways; all of them are linked to this page through its registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology