Joshi Jagtap Associates

Company or firm · 1 project · 1 MahaRERA registration

1Projects1 RERA registration
0Completedas reported on MahaRERA project pages
0%Kept RERA date0 of 1 past their proposed date, not extended
+25 moMedian delayvs RERA proposed date · 1 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Atul ViharP52100028039Pune (M Corp.)2021Certificate Signed28 Aug 202330 Sep 2025+25 months

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Atul Vihar+25 mo

Track record notes

  • 0 of 1 registration whose RERA proposed completion date has passed were never extended beyond it.
  • Longest extension on record: 25 months, for Atul Vihar (P52100028039).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology