Company or firm · 1 project · 2 MahaRERA registrations

1Projects2 RERA registrations
0Completedas reported on MahaRERA project pages
—Kept RERA dateno proposed date has passed yet
+4 moMedian delayvs RERA proposed date · 2 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Pradnyesh ShriniwasP52100050641Kharabwadi (Ct)2023Certificate Signed31 Dec 202730 Apr 2028+4 months
Pradnyesh ShriniwasPM1260002500160Kharabwadi (Ct)2025Certificate Signed31 Dec 202930 Apr 2030+4 months

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Pradnyesh Shriniwas+4 mo
  • Pradnyesh Shriniwas+4 mo

Track record notes

  • Longest extension on record: 4 months, for Pradnyesh Shriniwas (P52100050641).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology