Jhalak Constructions

Company or firm · 3 projects · 3 MahaRERA registrations

3Projects3 RERA registrations
0Completedas reported on MahaRERA project pages
—Kept RERA dateno proposed date has passed yet
+4 moMedian delayvs RERA proposed date · 3 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Jhalak FourwingsP51700047861Sai2022Certificate Signed31 Dec 203130 Apr 2032+4 months
Jhalak ArenaP51700048679Ulhasnagar (M Corp.)2023Certificate Signed31 Dec 202630 Apr 2027+4 months
Jhalak PalaciaP51700080091Ulhasnagar2025Certificate Signed31 Dec 202830 Apr 2029+4 months

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Jhalak Fourwings+4 mo
  • Jhalak Arena+4 mo
  • Jhalak Palacia+4 mo

Track record notes

  • Longest extension on record: 4 months, for Jhalak Fourwings (P51700047861).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology