Jeevandeep Developers
Company or firm · 2 projects · 2 MahaRERA registrations
2Projects2 RERA registrations
0Completedas reported on MahaRERA project pages
0%Kept RERA date0 of 2 past their proposed date, not extended
+71 moMedian delayvs RERA proposed date · 2 extended
0Regulatory casesMahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| VishramP51800014810 | Borivali | 2018 | Not reported | 31 Mar 2019 | 30 Jun 2026 | +87 months |
| Shri Yamai KrupaP51800014999 | Borivali | 2018 | Not reported | 31 Mar 2018 | 30 Oct 2022 | +55 months |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 0 of 2 registrations whose RERA proposed completion date has passed were never extended beyond it.
- Longest extension on record: 87 months, for Vishram (P51800014810).
- No MahaRERA regulatory order or list names these registrations.
Regulatory cases across projects
None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology