Jb Housing Llp

Company or firm · 2 projects · 2 MahaRERA registrations

2Projects2 RERA registrations
0Completedas reported on MahaRERA project pages
0%Kept RERA date0 of 2 past their proposed date, not extended
+22 moMedian delayvs RERA proposed date · 2 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Jb LifestyleP53100014234Sangli Miraj Kupwad (M Corp.)2017Not reported31 Mar 201930 Sep 2022+42 months
Jb PearlP53100024812Sangli Miraj Kupwad (M Corp.)2020Not reported30 Mar 202430 Apr 2024+1 month

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Jb Lifestyle+42 mo
  • Jb Pearl+1 mo

Track record notes

  • 0 of 2 registrations whose RERA proposed completion date has passed were never extended beyond it.
  • Longest extension on record: 42 months, for Jb Lifestyle (P53100014234).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology