Company or firm · 1 project · 1 MahaRERA registration

1Projects1 RERA registration
0Completedas reported on MahaRERA project pages
—Kept RERA dateno proposed date has passed yet
+4 moMedian delayvs RERA proposed date · 1 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Jayhind AmpleP52100055953Pimpri Chinchawad (M Corp.)2024Certificate Signed7 Apr 20277 Aug 2027+4 months

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Jayhind Ample+4 mo

Track record notes

  • Longest extension on record: 4 months, for Jayhind Ample (P52100055953).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology