Jay Somnath Builders And Developers
Company or firm · 2 projects · 2 MahaRERA registrations · 2 reported completed
Projects22 RERA registrations
Completed2as reported on MahaRERA project pages
Kept RERA date50%1 of 2 past their proposed date, not extended
Median delay+23 movs RERA proposed date · 1 extended
Regulatory cases0MahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| Somnath PalaceP50500013933 | Beltarodi | 2017 | Completed | 31 Dec 2017 | — | On date |
| Somnath Palace 2P50500013934 | Beltarodi | 2017 | Completed | 31 Dec 2018 | 30 Sep 2022 | +45 months |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 1 of 2 registrations whose RERA proposed completion date has passed was never extended beyond it.
- Longest extension on record: 45 months, for Somnath Palace 2 (P50500013934).
- No MahaRERA regulatory order or list names these registrations.
Regulatory cases across projects
None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology