Jay Somnath Builders And Developers

Company or firm · 2 projects · 2 MahaRERA registrations · 2 reported completed

Projects22 RERA registrations
Completed2as reported on MahaRERA project pages
Kept RERA date50%1 of 2 past their proposed date, not extended
Median delay+23 movs RERA proposed date · 1 extended
Regulatory cases0MahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Somnath PalaceP50500013933Beltarodi2017Completed31 Dec 2017—On date
Somnath Palace 2P50500013934Beltarodi2017Completed31 Dec 201830 Sep 2022+45 months

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Somnath PalaceOn date
  • Somnath Palace 2+45 mo

Track record notes

  • 1 of 2 registrations whose RERA proposed completion date has passed was never extended beyond it.
  • Longest extension on record: 45 months, for Somnath Palace 2 (P50500013934).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology