Jay Builders

Company or firm · 2 projects · 2 MahaRERA registrations

Projects22 RERA registrations
Completed0as reported on MahaRERA project pages
Kept RERA date0%0 of 1 past their proposed date, not extended
Median delay+24 movs RERA proposed date · 1 extended
Regulatory cases0MahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Proposed Redevelopment of Sugam ApartmentP51800007379Kurla2017Not reported12 Jan 201931 Dec 2022+47 months
Jay Celestial Redevelopment Vidharbha CHS LtdP51800027026Andheri2020Not reported31 Dec 2026—On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Proposed Redevelopment of Sugam Apartment+47 mo
  • Jay Celestial Redevelopment Vidharbha CHS LtdOn date

Track record notes

  • 0 of 1 registration whose RERA proposed completion date has passed were never extended beyond it.
  • Longest extension on record: 47 months, for Proposed Redevelopment of Sugam Apartment (P51800007379).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.