Jangid Properties

Company or firm · 2 projects · 2 MahaRERA registrations

2Projects2 RERA registrations
0Completedas reported on MahaRERA project pages
0%Kept RERA date0 of 2 past their proposed date, not extended
+35 moMedian delayvs RERA proposed date · 2 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Ambrosia and AsterP51700007248Mira Bhayandar (M Corp.)2017Not reported30 Apr 201929 Oct 2020+18 months
ArcadiaP51700008907Mirabhayandar (M Corp.)2017Not reported30 Apr 201831 Aug 2022+52 months

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Ambrosia and Aster+18 mo
  • Arcadia+52 mo

Track record notes

  • 0 of 2 registrations whose RERA proposed completion date has passed were never extended beyond it.
  • Longest extension on record: 52 months, for Arcadia (P51700008907).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology