Jaikumar Constructions Ltd
Company or firm · 7 projects · 9 MahaRERA registrations
7Projects9 RERA registrations
0Completedas reported on MahaRERA project pages
100%Kept RERA date3 of 3 past their proposed date, not extended
+4 moMedian delayvs RERA proposed date · 5 extended
0Regulatory casesMahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| Parksyde NestP51600025619 | Nashik | 2020 | Certificate Signed | 31 Dec 2027 | 30 Apr 2028 | +4 months |
| Parksyde NestP51600025620 | Nashik | 2020 | Certificate Signed | 31 Dec 2028 | 30 Apr 2029 | +4 months |
| Parksyde NestP51600025687 | Nashik | 2020 | Certificate Signed | 30 Jun 2026 | 30 Jun 2026 | On date |
| ShubharambhP51600030396 | Nashik (M Corp.) | 2021 | Certificate Signed | 31 Aug 2024 | 31 Aug 2024 | On date |
| Parksyde Nest Phase-3aP51600033065 | Nashik (M Corp.) | 2022 | Certificate Signed | 31 Dec 2025 | 31 Dec 2025 | On date |
| The Grand By Parksyde Phase - 1P51600034070 | Nashik | 2022 | Certificate Signed | 30 Apr 2027 | 30 Aug 2027 | +4 months |
| The Grand By Parksyde Phase - 2P51600034104 | Nashik | 2022 | Certificate Signed | 30 Apr 2027 | 30 Apr 2027 | On date |
| The Platinum Mall By ParksydeP51600052862 | Nashik (M Corp.) | 2023 | Certificate Signed | 31 May 2028 | 30 Sep 2028 | +4 months |
| Platinum Care By ParksydePC1220002502489 | Nashik | 2026 | Certificate Signed | 31 May 2028 | 30 Sep 2028 | +4 months |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 3 of 3 registrations whose RERA proposed completion date has passed were never extended beyond it.
- Longest extension on record: 4 months, for Parksyde Nest (P51600025619).
- No MahaRERA regulatory order or list names these registrations.
Regulatory cases across projects
None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology