Jaikumar Constructions Llp

Company or firm · 7 projects · 7 MahaRERA registrations · 6 reported completed

7Projects7 RERA registrations
6Completedas reported on MahaRERA project pages
100%Kept RERA date7 of 7 past their proposed date, not extended
+0 moMedian delayvs RERA proposed date · 0 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Parksyde Homes Phase 1P51600002640Nashik2017Completed30 Jun 2018—On date
Parksyde Homes Phase 2BP51600002975Nashik2017Completed30 Apr 2020—On date
Parksyde Homes Phase4AP51600003077Nashik2017Completed31 Mar 2019—On date
Parksyde Homes Phase 3P51600003548Nashik2017Certificate Signed30 Jun 202230 Jun 2022On date
Parksyde Homes Phase 5AP51600004799Nashik2017Completed30 Jun 2025—On date
Parksyde Homes Phase 4BP51600004804Nashik2017Completed31 Oct 2019—On date
Parksyde Homes Phase 2AP51600009429Nashik2017Completed30 Apr 2020—On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Parksyde Homes Phase 1On date
  • Parksyde Homes Phase 2BOn date
  • Parksyde Homes Phase4AOn date
  • Parksyde Homes Phase 3On date
  • Parksyde Homes Phase 5AOn date
  • Parksyde Homes Phase 4BOn date
  • Parksyde Homes Phase 2AOn date

Track record notes

  • 7 of 7 registrations whose RERA proposed completion date has passed were never extended beyond it.
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology