Jai Bhawani Orchid Infra Llp

Company or firm · 2 projects · 4 MahaRERA registrations

Projects24 RERA registrations
Completed0as reported on MahaRERA project pages
Kept RERA date0%0 of 2 past their proposed date, not extended
Median delay+6 movs RERA proposed date · 2 extended
Regulatory cases0MahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
VivantaP51700014993Kalher (Ct)2018Not reported30 Jun 202230 Jun 2023+12 months
Olivia BlissP51700046158Kalher (Ct)2022Not reported31 Dec 2026—On date
VivantaP51700054239Kalher (Ct)2024Not reported31 Aug 20231 Aug 2024+12 months
VivantaP51700076999Kalher (Ct)2024Not reported31 Dec 2028—On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Vivanta+12 mo
  • Olivia BlissOn date
  • Vivanta+12 mo
  • VivantaOn date

Track record notes

  • 0 of 2 registrations whose RERA proposed completion date has passed were never extended beyond it.
  • Longest extension on record: 12 months, for Vivanta (P51700014993).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology