Jagjit Estate & Devlopment Co. Pvt. Ltd

Company or firm · 2 projects · 2 MahaRERA registrations

2Projects2 RERA registrations
0Completedas reported on MahaRERA project pages
0%Kept RERA date0 of 2 past their proposed date, not extended
+16 moMedian delayvs RERA proposed date · 2 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Sudarshan Lands EndP51800000373Borivali2017Not reported31 Mar 201830 Nov 2019+20 months
Sudarshan LandmarkP51800030993Andheri2021Not reported31 Dec 202231 Dec 2023+12 months

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Sudarshan Lands End+20 mo
  • Sudarshan Landmark+12 mo

Track record notes

  • 0 of 2 registrations whose RERA proposed completion date has passed were never extended beyond it.
  • Longest extension on record: 20 months, for Sudarshan Lands End (P51800000373).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology