Jagdamba Developers And Builders

Company or firm · 2 projects · 2 MahaRERA registrations · 1 reported completed

Also appears as M/S JAGDAMBA DEVELOPERS AND BUILDERS

Projects22 RERA registrations
Completed1as reported on MahaRERA project pages
Kept RERA date100%2 of 2 past their proposed date, not extended
Median delay+0 movs RERA proposed date · 0 extended
Regulatory cases0MahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Gauri Gajanan ResidencyP51500016696Tisgaon2018Completed25 Aug 2019—On date
Guruganesh ResidencyP51500022287Tisgaon2019Not reported31 Jul 2022—On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Gauri Gajanan ResidencyOn date
  • Guruganesh ResidencyOn date

Track record notes

  • 2 of 2 registrations whose RERA proposed completion date has passed were never extended beyond it.
  • No MahaRERA regulatory order or list names these registrations.
  • MahaRERA records spell this promoter's name 2 ways; all of them are linked to this page through its registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology