Skip to content

Intofinity Promoters Private Limited

Company or firm · 8 projects · 11 MahaRERA registrations

8Projects11 RERA registrations
0Completedas reported on MahaRERA project pages
—Kept RERA dateno proposed date has passed yet
+4 moMedian delayvs RERA proposed date · 9 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Kohinoor KaleidoP52100046027Wagholi2022Certificate Signed30 Dec 202730 Apr 2028+4 months
Kohinoor RiverdaleP52100056021Wagholi2024Certificate Signed31 Dec 202831 Dec 2028On date
Kohinoor Central ParkP52100056358Man2024Certificate Signed31 Dec 202830 Apr 2029+4 months
Kohinoor Satori MahalungeP52100066472Man2024Certificate Signed31 Dec 202930 Apr 2030+4 months
Kohinoor KaleidoP52100078107Wagholi2024Certificate Signed15 Oct 202915 Feb 2030+4 months
Kohinoor WoodshireP52100078709Bhugaon2025Certificate Signed31 Dec 202931 Dec 2029On date
Kohinoor Central ParkP52100078767Man2025Certificate Signed15 Oct 202915 Feb 2030+4 months
Kohinoor RiverdaleP52100079217Wagholi2025Certificate Signed31 Dec 202830 Apr 2029+4 months
Kohinoor Royale TowersPR1260002501033Hinjavadi (Ct)2025Certificate Signed31 Dec 203030 Apr 2031+4 months
Kohinoor Woodshire Phase 2PR1261012501461Bhugaon2025Certificate Signed31 Dec 203030 Apr 2031+4 months
Kohinoor AvantaraPR1260002501984Tathwade2026Certificate Signed31 Mar 203231 Jul 2032+4 months
Show all 11 registrationsShow fewer

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Kohinoor Kaleido+4 mo
  • Kohinoor RiverdaleOn date
  • Kohinoor Central Park+4 mo
  • Kohinoor Satori Mahalunge+4 mo
  • Kohinoor Kaleido+4 mo
  • Kohinoor WoodshireOn date
  • Kohinoor Central Park+4 mo
  • Kohinoor Riverdale+4 mo
  • Kohinoor Royale Towers+4 mo
  • Kohinoor Woodshire Phase 2+4 mo
Show all 11 registrations
  • Kohinoor Avantara+4 mo

Track record notes

  • Longest extension on record: 4 months, for Kohinoor Kaleido (P52100046027).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology