Intella Homes

Company or firm · 6 projects · 6 MahaRERA registrations

6Projects6 RERA registrations
0Completedas reported on MahaRERA project pages
75%Kept RERA date3 of 4 past their proposed date, not extended
+0 moMedian delayvs RERA proposed date · 1 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Vardhaman ResidencyP52100012091Talegaon Dabhade (M Cl)2017Certificate Signed31 Mar 201931 Mar 2019On date
Vardhman SplendourP52100017125Wadagaon (Ct)2018Certificate Signed30 Dec 202130 Dec 2021On date
Vardhaman GoldP52100019944Wadagaon (Ct)2019Certificate Signed30 Jun 202130 Dec 2022+18 months
Vardhaman SquareP52100029216Varale2021Certificate Signed31 Dec 202831 Dec 2028On date
Mann SolitaireP52100046997Talegaon Dabhade (R)2022Certificate Signed31 Dec 202531 Dec 2025On date
Mann NaturaPR1260002602115Talegaon Dabhade (M Cl)2026Certificate Signed31 Dec 202931 Dec 2029On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Vardhaman ResidencyOn date
  • Vardhman SplendourOn date
  • Vardhaman Gold+18 mo
  • Vardhaman SquareOn date
  • Mann SolitaireOn date
  • Mann NaturaOn date

Track record notes

  • 3 of 4 registrations whose RERA proposed completion date has passed were never extended beyond it.
  • Longest extension on record: 18 months, for Vardhaman Gold (P52100019944).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology