Integrated Spaces Limited

Company or firm · 3 projects · 3 MahaRERA registrations

Projects33 RERA registrations
Completed0as reported on MahaRERA project pages
Kept RERA date33%1 of 3 past their proposed date, not extended
Median delay+12 movs RERA proposed date · 2 extended
Regulatory cases0MahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Integrated KamalP51800002437Kurla2017Not reported31 Dec 201831 Dec 2019+12 months
Integrated AhanaP51800002899Kurla2017Not reported30 Apr 202530 Apr 2025On date
Integrated IRS IIP52000005863Ulawe2017Not reported30 Sep 202030 Sep 2023+36 months

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Integrated Kamal+12 mo
  • Integrated AhanaOn date
  • Integrated IRS II+36 mo

Track record notes

  • 1 of 3 registrations whose RERA proposed completion date has passed was never extended beyond it.
  • Longest extension on record: 36 months, for Integrated IRS II (P52000005863).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology