Company or firm · 2 projects · 2 MahaRERA registrations

Also appears as M/S INDRAPRASTHA ASSOCIATES

2Projects2 RERA registrations
0Completedas reported on MahaRERA project pages
50%Kept RERA date1 of 2 past their proposed date, not extended
+12 moMedian delayvs RERA proposed date · 1 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
INDRAPRASTHA PHASE 2 Includes Building no. 5,9P52000018038Gondhalpada2018Not reported31 May 202130 May 2023+24 months
Indraprastha Building 6PR1270002500308Gondhalpada2025Not reported31 Dec 2025—On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • INDRAPRASTHA PHASE 2 Includes Building no. 5,9+24 mo
  • Indraprastha Building 6On date

Track record notes

  • 1 of 2 registrations whose RERA proposed completion date has passed was never extended beyond it.
  • Longest extension on record: 24 months, for INDRAPRASTHA PHASE 2 Includes Building no. 5,9 (P52000018038).
  • No MahaRERA regulatory order or list names these registrations.
  • MahaRERA records spell this promoter's name 2 ways; all of them are linked to this page through its registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology