Impressions Nxt

Company or firm · 4 projects · 4 MahaRERA registrations

Projects44 RERA registrations
Completed0as reported on MahaRERA project pages
Kept RERA date33%1 of 3 past their proposed date, not extended
Median delay+12 movs RERA proposed date · 2 extended
Regulatory cases0MahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
SilviaP51700023372Dombivli2019Not reported30 Dec 202331 Mar 2027+39 months
AthenaP51700023695Dombivli2020Not reported30 Dec 202431 Dec 2026+24 months
EvaanP51700031545Dombivli2021Not reported31 Jul 2026—On date
Om Shiv Ganesh Co Operative Housing Society LtdP51700055555Dombivli2024Not reported31 Mar 2027—On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Silvia+39 mo
  • Athena+24 mo
  • EvaanOn date
  • Om Shiv Ganesh Co Operative Housing Society LtdOn date

Track record notes

  • 1 of 3 registrations whose RERA proposed completion date has passed was never extended beyond it.
  • Longest extension on record: 39 months, for Silvia (P51700023372).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology