Imax Infra

Company or firm · 2 projects · 2 MahaRERA registrations

2Projects2 RERA registrations
0Completedas reported on MahaRERA project pages
0%Kept RERA date0 of 1 past their proposed date, not extended
+8 moMedian delayvs RERA proposed date · 2 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Royal GardenP99000005888Kurgaon2017Certificate Signed30 Jun 202730 Oct 2027+4 months
Royal GardenP99000023777Kurgaon2020Certificate Signed30 Dec 202431 Dec 2025+12 months

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Royal Garden+4 mo
  • Royal Garden+12 mo

Track record notes

  • 0 of 1 registration whose RERA proposed completion date has passed were never extended beyond it.
  • Longest extension on record: 12 months, for Royal Garden (P99000023777).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology