I Build Supreme Union Jv

Company or firm · 2 projects · 2 MahaRERA registrations

2Projects2 RERA registrations
0Completedas reported on MahaRERA project pages
0%Kept RERA date0 of 2 past their proposed date, not extended
+30 moMedian delayvs RERA proposed date · 2 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
ShubharambhP52100001406Hadapsar2017Certificate Signed31 Mar 201830 Sep 2020+30 months
Florista CountyP52100001416Hadapsar2017Certificate Signed31 Mar 201830 Sep 2020+30 months

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Shubharambh+30 mo
  • Florista County+30 mo

Track record notes

  • 0 of 2 registrations whose RERA proposed completion date has passed were never extended beyond it.
  • Longest extension on record: 30 months, for Shubharambh (P52100001406).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology