Hubtown Limited

Company or firm · 2 projects · 7 MahaRERA registrations

2Projects7 RERA registrations
0Completedas reported on MahaRERA project pages
43%Kept RERA date3 of 7 past their proposed date, not extended
+2 moMedian delayvs RERA proposed date · 4 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Hubtown GreenwoodsP51700000358Vartaknagar2017Not reported31 Jul 201930 Jan 2021+18 months
Hubtown GreenwoodsP51700000365Vartaknagar2017Not reported31 Jul 201830 Sep 2018+2 months
Hubtown GreenwoodsP51700000369Vartaknagar2017Not reported31 Jul 201930 Jan 2021+18 months
Hubtown GreenwoodsP51700000602Vartaknagar2017Not reported31 Jul 201930 Jan 2021+18 months
Hubtown Sunmist A 6th to Above FloorP51800001202Andheri2017Not reported31 Dec 2019—On date
Hubtown GreenwoodsP51700004458Vartaknagar2017Not reported31 Jul 2018—On date
Hubtown GreenwoodsP51700012016Vartaknagar2017Not reported31 Jul 2018—On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Hubtown Greenwoods+18 mo
  • Hubtown Greenwoods+2 mo
  • Hubtown Greenwoods+18 mo
  • Hubtown Greenwoods+18 mo
  • Hubtown Sunmist A 6th to Above FloorOn date
  • Hubtown GreenwoodsOn date
  • Hubtown GreenwoodsOn date

Track record notes

  • 3 of 7 registrations whose RERA proposed completion date has passed were never extended beyond it.
  • Longest extension on record: 18 months, for Hubtown Greenwoods (P51700000358).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology