Skip to content

Housing Development And Infrastructure Ltd

Company or firm · 9 projects · 14 MahaRERA registrations

9Projects14 RERA registrations
0Completedas reported on MahaRERA project pages
64%Kept RERA date9 of 14 past their proposed date, not extended
+0 moMedian delayvs RERA proposed date · 5 extended
14Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Premier ExoticaP51800004431Kurla2017Certificate Signed31 Jan 202131 Jan 2021On date
Majestic TowersP51800007283Kurla2017Certificate Signed30 Dec 202030 Dec 2020On date
Whispering Towers Efg WingsP51800007809Kurla2017Certificate Signed30 Nov 202030 Nov 2020On date
The NestP51800007814Kurla2017Certificate Signed31 Oct 201831 Oct 2019+12 months
Whispering Tower-AbcdP51800009742Kurla2017Certificate Signed30 Oct 202230 Oct 2022On date
Galaxy Apartments Cdf WingsP51800010758Kurla2017Certificate Signed31 Jan 202131 Jan 2021On date
Hdil Paradise CityP99000012466Mahim2017Certificate Signed30 Jun 201930 Jun 2019On date
Hdil Paradise City Sector 1,palgharP99000012536Mahim2017Certificate Signed30 Jan 201830 Jan 2019+12 months
Hdil Paradise CityP99000012539Mahim2017Certificate Signed30 Sep 201830 Sep 2019+12 months
Hdil Paradise CityP99000012576Mahim2017Certificate Signed30 Aug 201930 Aug 2019On date
Hdil Paradise CityP99000012642Mahim2017Certificate Signed30 Jun 201930 Jun 2019On date
Hdil Paradise CityP99000012735Mahim2017Certificate Signed30 Sep 201930 Sep 2019On date
Metropolis ResidencesP51800012577Andheri2017Certificate Signed31 Dec 201720 May 2018+5 months
Premier ExoticaP51800016598Kurla2018Certificate Signed31 Dec 201831 Dec 2019+12 months
Show all 14 registrationsShow fewer

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Premier ExoticaOn date
  • Majestic TowersOn date
  • Whispering Towers Efg WingsOn date
  • The Nest+12 mo
  • Whispering Tower-AbcdOn date
  • Galaxy Apartments Cdf WingsOn date
  • Hdil Paradise CityOn date
  • Hdil Paradise City Sector 1,palghar+12 mo
  • Hdil Paradise City+12 mo
  • Hdil Paradise CityOn date
Show all 14 registrations
  • Hdil Paradise CityOn date
  • Hdil Paradise CityOn date
  • Metropolis Residences+5 mo
  • Premier Exotica+12 mo

Track record notes

  • 9 of 14 registrations whose RERA proposed completion date has passed were never extended beyond it.
  • Longest extension on record: 12 months, for The Nest (P51800007814).

Regulatory cases across projects

Show all 14 cases
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology