Home Rising Construction LLP

Company or firm · 3 projects · 3 MahaRERA registrations

3Projects3 RERA registrations
0Completedas reported on MahaRERA project pages
33%Kept RERA date1 of 3 past their proposed date, not extended
+4 moMedian delayvs RERA proposed date · 2 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
VTP Aethereus- Phase1P52100026772Mahalunge2020Certificate Signed30 Jun 202630 Oct 2026+4 months
VTP Aethereus phase2P52100028131Mahalunge2021Certificate Signed30 Dec 202530 Dec 2025On date
Vtp Aethereus High StreetP52100055356Mahalunge2024Certificate Signed31 Mar 202531 Mar 2026+12 months

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • VTP Aethereus- Phase1+4 mo
  • VTP Aethereus phase2On date
  • Vtp Aethereus High Street+12 mo

Track record notes

  • 1 of 3 registrations whose RERA proposed completion date has passed was never extended beyond it.
  • Longest extension on record: 12 months, for Vtp Aethereus High Street (P52100055356).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology