Company or firm · 4 projects · 4 MahaRERA registrations

Also appears as HIRAY & JAGTAP ASSOCIATES

4Projects4 RERA registrations
0Completedas reported on MahaRERA project pages
100%Kept RERA date1 of 1 past their proposed date, not extended
+0 moMedian delayvs RERA proposed date · 0 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Shree Swastik Apartment Co-Op Housing SocietyP51600022646Nashik (M Corp.)2019Not reported30 Dec 2024—On date
Ayodhya Co Op Hsg Society LtdP51600031139Nashik (M Corp.)2021Not reported31 Mar 2028—On date
Bhavik Apartment Co. Op. Hsg. SocietyP51600048132Nashik (M Corp.)2022Not reported28 Oct 2028—On date
Shramvaibhav Co-Operative Housing Society LtdPR1220002500860Nashik2025Not reported31 Dec 2028—On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Shree Swastik Apartment Co-Op Housing SocietyOn date
  • Ayodhya Co Op Hsg Society LtdOn date
  • Bhavik Apartment Co. Op. Hsg. SocietyOn date
  • Shramvaibhav Co-Operative Housing Society LtdOn date

Track record notes

  • 1 of 1 registration whose RERA proposed completion date has passed was never extended beyond it.
  • No MahaRERA regulatory order or list names these registrations.
  • MahaRERA records spell this promoter's name 2 ways; all of them are linked to this page through its registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology