Hindustan Builders

Company or firm · 3 projects · 3 MahaRERA registrations

3Projects3 RERA registrations
0Completedas reported on MahaRERA project pages
100%Kept RERA date3 of 3 past their proposed date, not extended
+0 moMedian delayvs RERA proposed date · 0 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Dikshit Baug Apartment CP52100021390Pune City2019Certificate Signed30 Dec 202030 Dec 2020On date
Tarangan ApartmentsP52100051558Pune (M Corp.)2023Certificate Signed30 Mar 202430 Mar 2024On date
Vidula ApartmentsP52100076729Kothrud2024Certificate Signed30 Jun 202630 Jun 2026On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Dikshit Baug Apartment COn date
  • Tarangan ApartmentsOn date
  • Vidula ApartmentsOn date

Track record notes

  • 3 of 3 registrations whose RERA proposed completion date has passed were never extended beyond it.
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology