Hi Rock Construction Pvt Ltd
Company or firm · 3 projects · 3 MahaRERA registrations
Also appears as Hi Rock Construction Private Limited
3Projects3 RERA registrations
0Completedas reported on MahaRERA project pages
0%Kept RERA date0 of 1 past their proposed date, not extended
+0 moMedian delayvs RERA proposed date · 1 extended
0Regulatory casesMahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| Kinjal NineP51900004158 | Ward E | 2017 | Not reported | 19 Oct 2020 | 31 Aug 2024 | +46 months |
| Kinjal PrideP51900052854 | Ward Fsouth | 2023 | Not reported | 31 Oct 2026 | — | On date |
| Kinjal LegacyPR1170002601342 | Malabar Hill | 2026 | Not reported | 30 Jun 2029 | — | On date |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 0 of 1 registration whose RERA proposed completion date has passed were never extended beyond it.
- Longest extension on record: 46 months, for Kinjal Nine (P51900004158).
- No MahaRERA regulatory order or list names these registrations.
- MahaRERA records spell this promoter's name 2 ways; all of them are linked to this page through its registrations.
Regulatory cases across projects
None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology