Individual promoter · 4 projects · 4 MahaRERA registrations · 1 reported completed

4Projects4 RERA registrations
1Completedas reported on MahaRERA project pages
100%Kept RERA date3 of 3 past their proposed date, not extended
+0 moMedian delayvs RERA proposed date · 1 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Shilp SamruddhiP51600010415Nashik Road2017Completed30 Sep 2020—On date
Shilp SiddhiP51600011679Nashik Road2017Certificate Signed31 Dec 201931 Dec 2019On date
Shilp Swamini ApartmentP51600025113Nashik Road2020Certificate Signed30 Mar 202530 Mar 2025On date
Shilp MeridianP51600055808Nashik Road2024Certificate Signed31 Mar 202831 Jul 2028+4 months

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Shilp SamruddhiOn date
  • Shilp SiddhiOn date
  • Shilp Swamini ApartmentOn date
  • Shilp Meridian+4 mo

Track record notes

  • 3 of 3 registrations whose RERA proposed completion date has passed were never extended beyond it.
  • Longest extension on record: 4 months, for Shilp Meridian (P51600055808).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology