Harshmaan Spaces LLP

Company or firm · 3 projects · 3 MahaRERA registrations

3Projects3 RERA registrations
0Completedas reported on MahaRERA project pages
—Kept RERA dateno proposed date has passed yet
+0 moMedian delayvs RERA proposed date · 1 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Crescent HeightsP51800045723Borivali2022Certificate Signed31 Dec 202630 Apr 2027+4 months
Harshail Emerald ApartmentP51800056390Chinchvali2024Certificate Signed31 Jan 202731 Jan 2027On date
Harshail Iris ApartmentPM1180002501471Others2025Not reported30 Sep 2029—On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Crescent Heights+4 mo
  • Harshail Emerald ApartmentOn date
  • Harshail Iris ApartmentOn date

Track record notes

  • Longest extension on record: 4 months, for Crescent Heights (P51800045723).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology