Company or firm · 7 projects · 7 MahaRERA registrations

7Projects7 RERA registrations
0Completedas reported on MahaRERA project pages
100%Kept RERA date6 of 6 past their proposed date, not extended
+0 moMedian delayvs RERA proposed date · 0 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Hariom GloryP51600028656Nashik (M Corp.)2021Not reported30 Sep 2024—On date
Hariom GalaxyP51600030156Nashik (M Corp.)2021Not reported31 Mar 2024—On date
Hariom LandmarkP51600045250Nashik (M Corp.)2022Not reported31 Mar 2025—On date
Hariom EliteP51600046188Nashik (M Corp.)2022Not reported31 Mar 2025—On date
Hariom ParadiseP51600046509Nashik (M Corp.)2022Not reported31 Mar 2025—On date
Hariom EnclaveP51600051993Nashik (M Corp.)2023Not reported31 Mar 2026—On date
Hariom BlossomP51600080234Nashik (M Corp.)2025Not reported31 Mar 2027—On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Hariom GloryOn date
  • Hariom GalaxyOn date
  • Hariom LandmarkOn date
  • Hariom EliteOn date
  • Hariom ParadiseOn date
  • Hariom EnclaveOn date
  • Hariom BlossomOn date

Track record notes

  • 6 of 6 registrations whose RERA proposed completion date has passed were never extended beyond it.
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology