Haresh Girdharilal Gulrajani

Individual promoter · 2 projects · 2 MahaRERA registrations

2Projects2 RERA registrations
0Completedas reported on MahaRERA project pages
0%Kept RERA date0 of 2 past their proposed date, not extended
+12 moMedian delayvs RERA proposed date · 2 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Maruti RoyaleP51700033248Ulhasnagar (M Corp.)2022Certificate Signed30 Jun 202431 May 2025+11 months
Maruti ParadiseP51700033657Ulhasnagar (M Corp.)2022Certificate Signed30 Jun 202430 Jun 2025+12 months

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Maruti Royale+11 mo
  • Maruti Paradise+12 mo

Track record notes

  • 0 of 2 registrations whose RERA proposed completion date has passed were never extended beyond it.
  • Longest extension on record: 12 months, for Maruti Paradise (P51700033657).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology