Hare Krishna Enterprises

Company or firm · 4 projects · 4 MahaRERA registrations

Projects44 RERA registrations
Completed0as reported on MahaRERA project pages
Kept RERA date100%4 of 4 past their proposed date, not extended
Median delay+0 movs RERA proposed date · 0 extended
Regulatory cases0MahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Silver ArchP52000006858Ulawe2017Not reported31 Dec 2019—On date
Silver PalaceP52000016353Ulawe2018Not reported30 Dec 2021—On date
Silver SpringP52000022755Ulawe2019Not reported30 Dec 2023—On date
Silver CrestP52000023774Ulawe2020Not reported30 Dec 2023—On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Silver ArchOn date
  • Silver PalaceOn date
  • Silver SpringOn date
  • Silver CrestOn date

Track record notes

  • 4 of 4 registrations whose RERA proposed completion date has passed were never extended beyond it.
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology