H Rishabraj Developers

Company or firm · 3 projects · 3 MahaRERA registrations

3Projects3 RERA registrations
0Completedas reported on MahaRERA project pages
100%Kept RERA date2 of 2 past their proposed date, not extended
+0 moMedian delayvs RERA proposed date · 1 extended
1Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Samaj DarshanP51800010479Borivali2017Certificate Signed30 Apr 202330 Apr 2023On date
Rishabraj ViciniaP51800026330Kurla2020Certificate Signed29 Feb 202429 Feb 2024On date
Rishabraj AnujaPR1180002501316Borivali2025Certificate Signed30 Jun 202830 Oct 2028+4 months

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Samaj DarshanOn date
  • Rishabraj ViciniaOn date
  • Rishabraj Anuja+4 mo

Track record notes

  • 2 of 2 registrations whose RERA proposed completion date has passed were never extended beyond it.
  • Longest extension on record: 4 months, for Rishabraj Anuja (PR1180002501316).