H.K.Pujara Builders
Company or firm · 3 projects · 3 MahaRERA registrations
3Projects3 RERA registrations
0Completedas reported on MahaRERA project pages
67%Kept RERA date2 of 3 past their proposed date, not extended
+0 moMedian delayvs RERA proposed date · 1 extended
0Regulatory casesMahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| Chitralekha HerritageP51800004317 | Andheri | 2017 | Certificate Signed | 31 Mar 2019 | 31 Mar 2019 | On date |
| Orchid ResidencesP51800004540 | Andheri | 2017 | Certificate Signed | 31 Dec 2018 | 31 Dec 2018 | On date |
| Powai ProjectP51800004626 | Kurla | 2017 | Certificate Signed | 30 Dec 2023 | 31 Dec 2026 | +36 months |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 2 of 3 registrations whose RERA proposed completion date has passed were never extended beyond it.
- Longest extension on record: 36 months, for Powai Project (P51800004626).
- No MahaRERA regulatory order or list names these registrations.
Regulatory cases across projects
None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology