Skip to content

Gyandev Builders & Developers

Company or firm · 3 projects · 3 MahaRERA registrations

Also appears as GYANDEV BUILDERS AND DEVELOPERS

3Projects3 RERA registrations
0Completedas reported on MahaRERA project pages
100%Kept RERA date2 of 2 past their proposed date, not extended
+0 moMedian delayvs RERA proposed date · 0 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Shree Sai PanacheP51700000216Ambarnath2017Certificate Signed30 Dec 202030 Dec 2020On date
Anita Cooperative Housing Society Ltd.P51700014693Ambarnath2017Certificate Signed30 Nov 202030 Nov 2020On date
Om Shivanjali Chs LtdP51700078867Ambarnath (R)2025Not reported31 Oct 2027—On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Shree Sai PanacheOn date
  • Anita Cooperative Housing Society Ltd.On date
  • Om Shivanjali Chs LtdOn date

Track record notes

  • 2 of 2 registrations whose RERA proposed completion date has passed were never extended beyond it.
  • No MahaRERA regulatory order or list names these registrations.
  • MahaRERA records spell this promoter's name 2 ways; all of them are linked to this page through its registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology