Company or firm · 2 projects · 2 MahaRERA registrations

2Projects2 RERA registrations
0Completedas reported on MahaRERA project pages
0%Kept RERA date0 of 2 past their proposed date, not extended
+15 moMedian delayvs RERA proposed date · 2 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Guruprasdad Heights 2P53000003429Kolhapur (M Corp.)2017Not reported1 Jun 201930 Nov 2020+17 months
Guruprasad Heights 1P53000007923Kolhapur (M Corp.)2017Not reported31 Dec 201830 Dec 2019+12 months

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Guruprasdad Heights 2+17 mo
  • Guruprasad Heights 1+12 mo

Track record notes

  • 0 of 2 registrations whose RERA proposed completion date has passed were never extended beyond it.
  • Longest extension on record: 17 months, for Guruprasdad Heights 2 (P53000003429).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.