Guru Sai Developers

Company or firm · 5 projects · 5 MahaRERA registrations

5Projects5 RERA registrations
0Completedas reported on MahaRERA project pages
100%Kept RERA date5 of 5 past their proposed date, not extended
+0 moMedian delayvs RERA proposed date · 0 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Sai Shiv OmP52000017667Vadghar (Ct)2018Not reported1 Mar 2021—On date
Sai DeepP52000018838Vadghar (Ct)2018Not reported1 Mar 2021—On date
Sai EkviraP52000021107Vadghar (Ct)2019Not reported30 Dec 2021—On date
Samarth AanganP52000021801Vadghar (Ct)2019Not reported30 Mar 2022—On date
Sai PradneshP52000029813Vadghar (Ct)2021Not reported31 Mar 2023—On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Sai Shiv OmOn date
  • Sai DeepOn date
  • Sai EkviraOn date
  • Samarth AanganOn date
  • Sai PradneshOn date

Track record notes

  • 5 of 5 registrations whose RERA proposed completion date has passed were never extended beyond it.
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology