Guardian Promoters & Developers Private Limited

Company or firm · 3 projects · 4 MahaRERA registrations

3Projects4 RERA registrations
0Completedas reported on MahaRERA project pages
33%Kept RERA date1 of 3 past their proposed date, not extended
+12 moMedian delayvs RERA proposed date · 2 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Hill Shire - Phase 1P52100001572Wagholi2017Not reported31 Dec 201930 Jun 2022+30 months
Guardian AnantamP52100001833Kondhwa Bk2017Not reported30 Dec 2022—On date
Guardian Eastern MeadowsP52100003157Wagholi2017Not reported31 Dec 2026—On date
Guardian Eastern MeadowsP52100007435Wagholi2017Not reported30 Jun 202130 Jun 2023+24 months

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Hill Shire - Phase 1+30 mo
  • Guardian AnantamOn date
  • Guardian Eastern MeadowsOn date
  • Guardian Eastern Meadows+24 mo

Track record notes

  • 1 of 3 registrations whose RERA proposed completion date has passed was never extended beyond it.
  • Longest extension on record: 30 months, for Hill Shire - Phase 1 (P52100001572).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology