Gruha Navnirman Developers

Company or firm · 3 projects · 3 MahaRERA registrations

Projects33 RERA registrations
Completed0as reported on MahaRERA project pages
Kept RERA date33%1 of 3 past their proposed date, not extended
Median delay+3 movs RERA proposed date · 2 extended
Regulatory cases0MahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
ShabariP52100001736Pune (M Corp.)2017Not reported31 Mar 201830 Jun 2018+3 months
TrimurtiP52100001969Pune (M Corp.)2017Not reported31 Oct 201815 Feb 2021+28 months
IndrayanP52100001253Pune (M Corp.)2017Not reported31 Dec 2017—On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Shabari+3 mo
  • Trimurti+28 mo
  • IndrayanOn date

Track record notes

  • 1 of 3 registrations whose RERA proposed completion date has passed was never extended beyond it.
  • Longest extension on record: 28 months, for Trimurti (P52100001969).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology