Green Space Developers

Company or firm · 1 project · 2 MahaRERA registrations

1Projects2 RERA registrations
0Completedas reported on MahaRERA project pages
50%Kept RERA date1 of 2 past their proposed date, not extended
+6 moMedian delayvs RERA proposed date · 1 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Angel HillP52100007681Talegaon Dabhade (M Cl)2017Certificate Signed30 Mar 201830 Mar 2019+12 months
Angel HillP52100015702Talegaon Dabhade (M Cl)2018Certificate Signed31 Mar 201931 Mar 2019On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Angel Hill+12 mo
  • Angel HillOn date

Track record notes

  • 1 of 2 registrations whose RERA proposed completion date has passed was never extended beyond it.
  • Longest extension on record: 12 months, for Angel Hill (P52100007681).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology