Green Developers Llp
Company or firm · 1 project · 2 MahaRERA registrations
1Projects2 RERA registrations
0Completedas reported on MahaRERA project pages
—Kept RERA dateno proposed date has passed yet
+4 moMedian delayvs RERA proposed date · 2 extended
0Regulatory casesMahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| Ranbir Green PathP51800079703 | Goregaon | 2025 | Certificate Signed | 28 Jan 2029 | 28 May 2029 | +4 months |
| Ranbir Green PathP51800080759 | Goregaon | 2025 | Certificate Signed | 28 Jan 2029 | 28 May 2029 | +4 months |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- Longest extension on record: 4 months, for Ranbir Green Path (P51800079703).
- No MahaRERA regulatory order or list names these registrations.
Regulatory cases across projects
None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology