Green City Builders

Company or firm · 1 project · 2 MahaRERA registrations

1Projects2 RERA registrations
0Completedas reported on MahaRERA project pages
0%Kept RERA date0 of 2 past their proposed date, not extended
+48 moMedian delayvs RERA proposed date · 2 extended
1Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Amans MannatP50500008476Nagpur (M Corp.)2017Active20 Apr 202131 Mar 2027+71 months
Amans MannatP50500048603Nagpur (M Corp.)2023Certificate Signed21 Mar 202531 Mar 2027+24 months

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Amans Mannat+71 mo
  • Amans Mannat+24 mo

Track record notes

  • 0 of 2 registrations whose RERA proposed completion date has passed were never extended beyond it.
  • Longest extension on record: 71 months, for Amans Mannat (P50500008476).

Regulatory cases across projects

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology