Skip to content

Graffic Infrastructure Pvt. Ltd

Company or firm · 2 projects · 2 MahaRERA registrations

Also appears as GRAFFIC INFRASTRUCTURE PVT. LTD.

2Projects2 RERA registrations
0Completedas reported on MahaRERA project pages
50%Kept RERA date1 of 2 past their proposed date, not extended
+12 moMedian delayvs RERA proposed date · 1 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Suvarnaneel Housing StreetP51500019798Devlai2019Certificate Signed30 Mar 202530 Mar 2027+24 months
Suvarnaneel Housing ParkP51500027003Devlai2020Certificate Signed30 Jun 202630 Jun 2026On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Suvarnaneel Housing Street+24 mo
  • Suvarnaneel Housing ParkOn date

Track record notes

  • 1 of 2 registrations whose RERA proposed completion date has passed was never extended beyond it.
  • Longest extension on record: 24 months, for Suvarnaneel Housing Street (P51500019798).
  • No MahaRERA regulatory order or list names these registrations.
  • MahaRERA records spell this promoter's name 2 ways; all of them are linked to this page through its registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology