Gowardhan Builders & Developers
Company or firm · 3 projects · 3 MahaRERA registrations
3Projects3 RERA registrations
0Completedas reported on MahaRERA project pages
100%Kept RERA date3 of 3 past their proposed date, not extended
+0 moMedian delayvs RERA proposed date · 0 extended
0Regulatory casesMahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| Vaibhav RatnaP52800016869 | Nachane (Ct) | 2018 | Not reported | 30 Dec 2022 | — | On date |
| ShrirangaiP52800025362 | Nachane (Ct) | 2020 | Certificate Signed | 28 Aug 2023 | 28 Aug 2023 | On date |
| ShrivishwaP52800032376 | Nachane (Ct) | 2022 | Certificate Signed | 31 Dec 2024 | 31 Dec 2024 | On date |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 3 of 3 registrations whose RERA proposed completion date has passed were never extended beyond it.
- No MahaRERA regulatory order or list names these registrations.
Regulatory cases across projects
None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology