Company or firm · 3 projects · 3 MahaRERA registrations

3Projects3 RERA registrations
0Completedas reported on MahaRERA project pages
100%Kept RERA date3 of 3 past their proposed date, not extended
+0 moMedian delayvs RERA proposed date · 0 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Vaibhav RatnaP52800016869Nachane (Ct)2018Not reported30 Dec 2022—On date
ShrirangaiP52800025362Nachane (Ct)2020Certificate Signed28 Aug 202328 Aug 2023On date
ShrivishwaP52800032376Nachane (Ct)2022Certificate Signed31 Dec 202431 Dec 2024On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Vaibhav RatnaOn date
  • ShrirangaiOn date
  • ShrivishwaOn date

Track record notes

  • 3 of 3 registrations whose RERA proposed completion date has passed were never extended beyond it.
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology