Gopal Krishna Developers

Company or firm · 5 projects · 5 MahaRERA registrations

5Projects5 RERA registrations
0Completedas reported on MahaRERA project pages
100%Kept RERA date2 of 2 past their proposed date, not extended
+4 moMedian delayvs RERA proposed date · 3 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Krishna NisargaP51700006472Kalyandombivali (M Corp.)2017Certificate Signed30 May 202331 Dec 2021On date
Krishna ParadiseP51700012318Kalyandombivali (M Corp.)2017Certificate Signed30 Jun 201930 Jun 2019On date
Krishna SquareP51700013776Netivali2017Certificate Signed31 Jul 202730 Nov 2027+4 months
Krishna AnandP51700031006Tisgaon2021Certificate Signed31 Dec 202630 Apr 2027+4 months
Gaondevi CrownP51700031502Tisgaon2021Certificate Signed31 Dec 202630 Apr 2027+4 months

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Krishna NisargaOn date
  • Krishna ParadiseOn date
  • Krishna Square+4 mo
  • Krishna Anand+4 mo
  • Gaondevi Crown+4 mo

Track record notes

  • 2 of 2 registrations whose RERA proposed completion date has passed were never extended beyond it.
  • Longest extension on record: 4 months, for Krishna Square (P51700013776).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology